- Core drilling & cutting of the concrete floor continues in the Garden Level. Residents will experience noise and vibrations. Work will begin as early as 7:00 am. Thank you for your understanding and patience.
- Construction work on the 23rd, 25th, and 26th Tier apartments will continue.
- Construction demolition work will continue in the Auditorium.
- First floor work in the lobby area continues.
- Abatement work in the partitioned area around the old resident storage room to the bathroom continues from 4th floor to 8th floor.
- On Thursday, July 12, 2018, a water shutdown is planned for Culpepper Garden I from 9:00 pm to to 5:00 am to install a new sanitary line in the Garden Level. Residents are encourage to minimize flushing overnight.
- On Wednesday July 18, 2018, a power shutdown is planned for the West Wing of Culpepper Garden from 8:00 a.m to 8:00 p.m.
- Remember safety is first. Do not enter construction areas.
Call the Renovation Telephone Line at 571-699-3830 for an audio version of this bulletin.
Relocation related questions: Contact Escarleth Torres-Shahin
703-642-3830 ext. 327 or email etorres@whdc.org
Construction related questions: Contact Doug Schroeder
703-528-0162 ext. 117 or email dschroeder@culpeppergarden.org
Report maintenance needs or for lease related questions: talk to the Management Office by calling 703-528-0162.
Si usted necesita una traducción en español de este boletín, comuníquese con Escarleth Torres-Shahin:
Escarleth Torres-Shahin,
Resident Relations Liaison
etorres@whdc.org
703-642-3830